Watermain Replacement at the Intersection of Bathurst & Queen’s Quay

Watermain Replacement at the Intersection of Bathurst & Queen’s Quay

Watermain Replacement at the Intersection of Bathurst & Queen’s Quay

Work re-start Date: Nov 6, 2017

Expected End Date:  December 15, 2017

Permanent Restoration / Paving: Spring 2018

*Timeline is subject to change.

The City of Toronto is returning to complete the final portion of the watermain replacement that started in 2016. The portion of work in the intersection of Bathurst and Queen’s Quay required re-designs due to the soil conditions and location of other utilities.

Work will start on Nov 6, using an open trench to install and connect this new section of watermain to the watermain that was installed in 2016. We appreciate your patience as we work to complete this important infrastructure upgrade.

WHAT TO EXPECT DURING CONSTRUCTION

You will experience dust, noise and other inconveniences. The City will make efforts to reduce impacts.

Work Hours:
Monday to Friday 7:00 a.m. to 7:00 p.m.
Saturday and Sunday as required.

Pedestrian Access: During work hours, due to the nature of the work and for safety reasons, pedestrians will not be able to use the west crosswalk of Bathurst and Queen’s Quay at time. Please abide by the signs and take precautions walking over the steel plates that will cover the trench.

Traffic Management: Road users should expect delays and increased traffic on nearby main and side streets (see page 3 for traffic management details).

Martin Goodman Trail:  will be affected during phase 2 work, cyclist are advised to abide by signage during this work and take precautions riding over the steel plates are installed to cover the trench.

Deliveries: Businesses may want to consider adjusting delivery times as a result of the lane restrictions during this project. Please discuss your delivery concerns with the Field Ambassador.

Road and Sidewalk Access: In order to complete the work in a safe manner, there will be road and sidewalk restrictions within the construction work area. Access to businesses will be maintained.

Driveway Access: The contractor will notify you of any temporary restrictions to your driveway access. If your property has two entrances, one entrance will be kept open at all times. Access for emergency vehicles will be maintained at all times.

Accommodation: Residents that require accommodation must contact the project manager to arrange for access during construction.

Restoration: In order to restore the road/sidewalk, temperatures must be consistently above 7 degrees. As such, the City will return in Spring 2018 when asphalt and concrete plants open to complete the permanent restoration of areas affected by construction.

Map of affected area: