Construction and Road Closures
The Waterfront BIA has worked to aggregate current and upcoming construction notices from various sources, including The City of Toronto, Waterfront Toronto, and Toronto Hydro.
As a representative of the business community through the area, the Waterfront BIA seeks to advocate to ensure that these projects are completed quickly and on time, and with a limited impact on people’s enjoyment of the waterfront.
Last Updated: October 14, 2026
Toronto Hydro - 215 Lake Shore Boulevard East
Constructor: Toronto Hydro
Location: A section of Lake Shore Boulevard East and Lower Sherbourne Street
Anticipated Completion: December 2026
Area Impacts: Road and sidewalk restrictions, possible power interruptions, construction noise, excavation
More Information:
Toronto Hydro Capital Projects — (416) 542-3366
capitalprojects@torontohydro.com
Construction Notice: View notice
Notice Date: December 8, 2025
Quayside Infrastructure and Public Realm
Constructor: Eastern Construction for Waterfront Toronto
Location: Queens Quay East, Small Street, and Parliament Street to Lake Shore Boulevard East
Anticipated Completion: December 2026 for the current infrastructure and public realm phase, subject to change
What's Happening: Waterfront Toronto is upgrading underground infrastructure, roadways and public spaces in the Quayside neighbourhood.
Area Impacts: Small Street is fully closed, the Queens Quay East north sidewalk is closed, and the westbound curb lane is reduced — this closure regime is in effect from October 4 to December 31, 2026. Further short-term lane restrictions and pedestrian/cycling pathway shifts will be announced by notice as later phases proceed. Expect construction traffic, flaggers, dust, and noise around the work zones while the project continues to December 2026.
Construction Notices: Notice #4, Notice #6.2
More Information:
Notice Date: May and September 2026; sources reviewed October 14, 2026
Quayside Site Development
Constructor: CentreCourt Constructors Inc. for Dream Unlimited
Location: 259 and 291 Lake Shore Boulevard East, between Bonnycastle Street and Small Street; parking lot at 200 Queens Quay East
Anticipated Completion: Construction of new developments is expected to begin in 2026. Overall development is staged; the linked notices do not give an overall completion date.
What's Happening: The Quayside development lands are being prepared for construction of new homes.
Area Impacts: The parking lot at 200 Queens Quay East closed permanently on August 31, 2026, to support the next phase of construction.
Construction Notices: Notice #2, Notice #3
More Information:
Notice Date: June and August 2026
Ferry Fleet Replacement — Jack Layton Ferry Terminal
Constructor: City of Toronto; CreateTO manages construction delivery, with Toronto Hydro installing the power supply
Location: Jack Layton Ferry Terminal, 9 Queens Quay West
Anticipated Completion: December 2026 for shoreside construction; the second new ferry is scheduled to arrive in spring 2027
What's Happening: New electrical infrastructure, charging towers and dock improvements are being installed to support Toronto’s new electric ferries.
Area Impacts: Regular passenger ferry service continues throughout construction. Commercial vehicle ferry service to the Islands may be interrupted at times. Construction of charging tower supports and dock/electrical work is underway at the terminal.
More Information:
Notice Date: Project webpage updated March 11, 2026
Billy Bishop Toronto City Airport — Runway End Safety Areas (RESA)
Constructor: EllisDon Civil Ltd. for Toronto Port Authority, with Stantec and J.F. Baird
Location: Billy Bishop Toronto City Airport, Toronto Islands — both ends of Runway 08/26
Anticipated Completion: July 2027 for RESA compliance; airfield restoration continues through late fall 2027, with habitat restoration and shoreline enhancement continuing in 2028
What's Happening: New safety areas are being constructed at both ends of the airport’s main runway to meet federal aviation safety requirements.
Area Impacts: Work is generally scheduled overnight (11 p.m.–6 a.m., Monday to Saturday), with staging from 9 p.m.; material deliveries may occur around the clock. Emergency medical helicopter operations will continue. Most construction materials and workers will arrive by water from the Port Lands, avoiding Eireann Quay and the airport ferry. Marine construction equipment will be visible in the Inner Harbour.
More Information:
Notice Date: June 30, 2026
Port Lands Flood Protection and Lake Shore Boulevard East
Constructor: EllisDon for Waterfront Toronto
Location: Port Lands, including Lake Shore Boulevard East between Cherry Street and Carlaw Avenue, Cherry Street and Commissioners Street
Anticipated Completion: 2026 for the Lake Shore Boulevard East works; other Port Lands projects have separate schedules
What's Happening: With the main flood protection works complete, Waterfront Toronto is completing remaining road improvements and cycling connections in the Port Lands and along Lake Shore Boulevard East.
Area Impacts: Road and lane restrictions, traffic delays, cycling detours and Lower Don Trail detours.
Construction Notices: Notice #67
More Information:
Notice Date: See all individual notices here
Broadview and Eastern Flood Protection
Constructor: PCL Construction for Waterfront Toronto
Location: Eastern Avenue, Broadview Avenue, and Sunlight Park Road, east of the Don River
Anticipated Completion: The activities in Notice #10 are scheduled through November 30, 2026; this is not the overall project completion date
What's Happening: Crews are excavating, demolishing buildings and carrying out utility work to construct flood protection infrastructure east of the Don River.
Area Impacts: Evening and Overnight Construction (5 PM–3 AM), Construction Noise, Concrete Cutting, Heavy Equipment, Excavation
Construction Notices: Notice #10
More Information:
Notice Date: September 2026
Notes:
The Waterfront BIA is not the constructor of any of these projects and aggregates this information as a courtesy to its members. As such, the information may be incomplete, incorrect, or out of date. Please reach out to the contact noted in the linked construction notices if you have any questions or concerns regarding this work, and review the below-linked websites for further information on these and other construction projects through the area. If you have any questions or concerns, please get in touch with Oliver Hierlihy, Director, Operations: oliver@waterfrontbia.com
Individual Port Lands notices are not listed; only major Port Lands work with a direct effect on waterfront access is noted above. Please see Waterfront Toronto's Port Lands construction notices for the full list.
Further Information:
Waterfront Toronto — Quayside project and construction notices: Project page; Construction updates
Waterfront Toronto — Port Lands: Project page; Construction updates
City of Toronto — Ferry Fleet Replacement: Project page
City of Toronto — Gardiner Expressway Strategic Rehabilitation Plan: Project page
Toronto Port Authority — Runway End Safety Areas: Project page
Toronto Hydro — construction information: Planning and construction
City of Toronto — Spadina–Fort York construction notices; Infrastructure & Construction Projects; TOinview Project Map; Road Restrictions
TTC — Construction Notices
Enbridge Gas — Projects