From: gnayot@ellisdon.com [mailto:gnayot@ellisdon.com]
Sent: March 14, 2011 5:25 PM
Subject: CONSTRUCTION NOTICE 7: YORK QUAY REVITALIZATION UNDERGROUND GARAGE
Please note that the following construction activities are scheduled to
commence Monday March 14 and Tuesday March 15, 2011.
. Please note that due to an unforeseen logistical issue in our
sequence of construction, selected trucks have needed to exit using the
Brookfield lane as opposed to our temporary Road. This activity may
potentially continue tomorrow morning as well. We realize that trucks
leaving via Brookfields property may track some dirt and therefore have
been keeping on top of the issue by sweeping the roads.
We do wish to apologize for any inconvenience this may cause. We will do
our best to keep the road clean.
Please advise your residents and tenants about this planned activity AS
APPROPRIATE. For more information about the project, please visit
www.waterfrontoronto.ca or www.harbourfrontcentre.ca.
Please contact me if you should have any questions or concerns.
Regards,
Gali Nayot
EllisDon Corporation
Tel: (416) 214-1375
Cell.(416) 881-1235
gnayot@ellisdon.com